An ERP demo proves that the vendor knows how to present its product. It does not prove that the product will handle your business rules, your volumes and your exceptions. When two or three vendors are left on the shortlist and the stakes run to several years of budget, there is a more reliable tool than the demo: the ERP proof of concept (POC), a bounded pilot of six to eight weeks, run on your data, with success criteria written down before day one.
This guide is for CIOs and CFOs of mid-sized companies who have to make the call. It explains when to run a POC, how to scope it, put it under contract and organize it, and then how to read the results without being trapped by a “showcase” POC.
Demo, POC, Pilot, MVP: Four Terms You Should Not Mix Up
All four terms appear in vendor proposals as if they were interchangeable. They are not, and the confusion is expensive: you think you have “tested” the system when you have only watched it.
| Term | Who drives | Data | Goal | Typical duration |
|---|---|---|---|---|
| Demo | The vendor | Fictitious or generic | Present the product and the scenario | A few hours to 2 days |
| POC (proof of feasibility) | The vendor and your key users, together | Anonymized extract of your data | Prove that the riskiest scenarios work | 6 to 8 weeks |
| Pilot | Your users | Real data, reduced scope | Validate real-world use (one site, one entity) | Several months |
| MVP | Your users | Real data | First usable version, in production | Several months |
In this article, “POC” and “pre-signing pilot” mean the second row: a short phase located before the license and integration contract, whose only purpose is to inform a decision. The pilot in the strict sense (one site or entity live in production) and the MVP belong to the project itself, once the decision has been made. For the demo phase that comes before, see our guide to preparing and scoring an ERP demo.
When a POC Is Worth It (and When It Is a Waste of Time)
A POC ties up your best business users for several weeks. It is not free, even when the vendor does not charge for it. It is justified when the risk it covers is greater than its cost.
Situations Where It Is Justified
- A differentiating process that standard ERP does not cover out of the box: make-to-order production with variant bills of materials, progress billing, lot and traceability management, multi-currency intercompany.
- A history of gaps between demo and reality on a previous project: if your last project revealed “planned” features that turned out to be missing, the POC is insurance.
- A tight race between two vendors after the scoring grid: instead of choosing on gut feeling, you separate them with evidence.
- Critical interfaces (EDI, e-commerce, MES, payroll) whose technical feasibility drives the schedule.
- High financial stakes relative to the cost of the POC: the longer the contract commits you, the more profitable up-front proof becomes.
The Two Cases Where You Should Skip It
- A standard need with a simple scope. If your processes are close to common practice and comparable, reachable references exist, a POC will add little. Reference calls and a well-scripted demo are enough.
- A vendor that has not been qualified yet. The POC is the final step of selection, not the first. Running a POC with five vendors exhausts your teams and dilutes your results. Limit yourself to two, three at most.
Do not run a POC just to “get a feel” for the product either. Without a hypothesis to validate, it becomes free training for your teams and a sales exercise for the vendor.
Defining the Scope: 3 to 5 End-to-End Scenarios, No More
Scope is the most structuring decision. Too broad, and the POC becomes a disguised project that never ends. Too narrow, and it proves nothing. The practical rule: three to five end-to-end scenarios, no more.
An end-to-end scenario crosses several modules and ends with a verifiable result. Example: order-to-cash (order, stock availability, shipment, invoice, accounting entry, reconciliation). It is not a feature checklist, it is a business sequence with its edge cases.
Choose the Riskiest Scenarios, Not the Easiest
This is the main trap. The vendor naturally proposes the scenarios where its product shines: entering a standard order, a demo dashboard. You must impose the opposite. For each candidate, ask two questions:
- Is this scenario critical to the business (revenue, compliance, customer lead time)?
- Is there a serious reason to doubt that the ERP covers it as standard (unusual business rule, volume, complex interface)?
Scenarios that answer yes to both questions go into the POC. Those that answer no to both stay out: they will be validated during the project. Make sure to include at least one exception scenario (return, credit note, stock-out, interface error), because that is where gaps hide.
To formalize this, write a one-page sheet for each scenario: trigger, steps, input data, expected result, specific business rules, actors. These sheets draw on the requirements of your ERP requirements document: if the requirements document does not exist yet, the POC is the wrong moment to improvise one.
Data Set: Anonymized Extract, Minimum Representative Volume
A POC on fictitious data is still a demo. Insist on a data set taken from your systems:
- Anonymized extract: names of customers, suppliers and employees and bank details replaced, but structure, quirks and inconsistencies preserved. Duplicates, badly coded items and exceptional price lists are part of the test. Have your data protection officer validate the anonymization before any transfer, especially if the data leaves the European Union or passes through a vendor subcontractor.
- Minimum representative volume: you do not need to migrate everything, but the volume must be large enough to observe realistic behavior. If your catalog holds tens of thousands of SKUs or your monthly postings are massive, a sample of a few hundred rows will say nothing about performance. Agree the threshold to test with the vendor and record it in the scoping document.
- A load test: how the vendor loads your data is itself information. How many iterations? What manual rework? Which anomalies were detected? It is a preview of the migration in the real project.
Measurable Success Criteria Before Kickoff: The Go/No-Go Scorecard
A success criterion written after the POC is a criterion of convenience. Before kickoff, each scenario gets measurable criteria, signed by the sponsor and the vendor. The grid below is a template; the thresholds must be adapted to your context.
| Criterion | Measure | Threshold to set before the POC |
|---|---|---|
| Functional coverage | Scenario steps completed in standard, without custom development | Minimum share of steps in standard, 100% on critical steps |
| Gaps | Number of gaps classed as blocking, major, minor | Zero unresolved blocking gaps, cap on major gaps without a documented solution |
| User autonomy | Steps performed by your key users without the vendor at the controls | Minimum threshold per scenario, measured in weeks 5 to 8 |
| Accuracy of results | Differences between ERP result and reference result (stock, margin, postings) | Tolerance defined by the CFO, zero unexplained differences |
| Performance | Processing time on the agreed volume (period close, MRP, import) | Maximum acceptable time set by the business |
| Interfaces | End-to-end flow with the third-party system | Flow succeeds on the agreed test set |
Three rules to make the scorecard really work:
- Weight the criteria: a blocking gap on a critical process outweighs ten minor gaps.
- Set the decision rule in advance: go if all critical criteria are met, conditional go with a costed action plan if only secondary criteria are missed, no-go otherwise.
- Forbid threshold revisions along the way, except with the sponsor’s written agreement. A threshold that drops when the result is poor no longer measures anything.
Contract Framework: Who Pays, Duration, Ownership of Deliverables, Exit Clause
A POC without a written framework quickly turns ambiguous. A short engagement letter or POC contract is enough, but it must cover five points.
- Who pays. Practices vary: free POC in exchange for a quick decision, POC billed on time spent, or shared costs. A free POC is not always an advantage: the vendor then puts sales resources on it rather than its best consultants, and expects implicit exclusivity in return. A paid POC creates a cleaner relationship, with a contractual deliverable.
- Duration and milestones. Six to eight weeks, with a firm end date, a mid-point review and a dated decision meeting. Write down what happens if the vendor does not deliver on time.
- Ownership of deliverables. Scenario sheets, configuration work, data sets, the gap log and the final report must belong to you, whatever the outcome. Otherwise your teams’ work enriches the vendor and leaves you empty-handed.
- Confidentiality and data. Non-disclosure commitment, anonymization rules, hosting location of the data set and an obligation to delete at the end of the POC, with written confirmation.
- Exit clause. The POC commits you to no purchase. State in black and white that a no-go outcome entitles the vendor to no compensation, and that the prices offered during the POC remain valid for a defined period if you proceed. For the contract that follows, see the 15 clauses to check before signing an ERP contract.
Organization: Client Team, Sponsor, Weekly Rituals, Gap Log
The quality of a POC depends more on your organization than on the vendor.
The client team. A POC project manager (often IT or a methods lead), one key user per scenario, a finance representative to validate accounting results, and a technical lead for data and interfaces. Each key user must be genuinely available: if they keep their full-time job on top of the POC, the POC will drift. Negotiate their workload with their managers before launch.
The sponsor. A member of senior management (CFO, CEO or CIO) who validates the scope, arbitrates disagreements and owns the final decision. Without a sponsor, nobody decides when the POC reveals an awkward gap.
The rituals.
- A one-hour weekly meeting with the vendor: progress by scenario, open gaps, risks.
- A mid-point review workshop, where the key users perform the operations themselves.
- A final readout in front of the sponsor, with the go/no-go scorecard filled in scenario by scenario.
The gap log. This is the most valuable deliverable. For each gap: scenario concerned, description, severity, cause (standard feature missing, configuration possible, development needed), solution proposed by the vendor, estimated cost and lead time, status. This log will later feed the requirements document, the schedule and the price negotiation.
Also keep key users at the controls from the second half of the POC. A POC where only the vendor’s consultants operate the tool measures their talent, not usability or adoption.
Reading the Results: Five Red Flags
POC results are not read only in the scorecard. Some behaviors, observed along the way, say a lot.
- The vendor “configures on behalf of” users. If, at every step, the consultant takes the mouse while your key users watch, you are not testing the tool: you are sitting through an extended demo. Measure the share of steps performed by your teams. A tool that only its vendor can operate will pose the same problem in production.
- Gaps are closed with custom development. Every customization is a cost, a maintenance risk and a drag on version upgrades. A scorecard where every gap is “resolved” by custom code is not a green scorecard.
- “We’ll see during the project” keeps coming up. A gap pushed to the build phase is not resolved, it is postponed, and its cost will be billed to you later, when your negotiating leverage has gone.
- The data set is reworked behind the scenes. If the vendor quietly cleans your data to get a better result, you will only see the anomalies at migration. Require traceability of every data transformation.
- Resources change midway. The senior consultant from the first meetings disappears, replaced by a junior. It is a direct indicator of what project staffing will look like. Write the names and profiles of the people involved into the POC contract.
A “showcase” POC often combines several of these signals: scope chosen by the vendor, smoothed data, expert consultants at the controls. The result is flattering and has no predictive value. The countermeasure comes down to three points: scenarios imposed by you, data from your own systems, users who do the manipulating.
From POC to Contract: Reusing What You Learned in the Requirements and the Schedule
A good POC does not end with a decision. It produces material you can reuse afterwards.
- The requirements document. Validated scenario sheets become proven functional specifications. Documented gaps become precise requirements, with the expected level of response (standard, configuration, development).
- The schedule. The time actually spent on each scenario gives an estimation base far more reliable than sales quotes. If a scenario took three times the planned time, apply that ratio to the project schedule.
- Price negotiation. Every gap requiring development or an add-on module is a costed argument. Put it to the vendor: “this point was not covered as standard, so it must be included in the offer or offset in the price.” A gap documented during the POC can be negotiated; a gap discovered at acceptance testing has to be endured.
- Commitments. Carry into the contract the promises made during the POC: announced features, fix lead times, consultant profiles. What is not written in the contract binds no one.
- Choosing the integrator. If the integrator is not the vendor, involve them in the POC or at least in the readout. See our integrator scoring framework to compare candidates.
POC Budget: A Calculation Logic, Not a Figure
Rather than a generic amount, build your budget from effort:
- Vendor side: number of scenarios × consultant days per scenario (preparation, configuration, support) + data loading + management. Ask the vendor for this breakdown even if the POC is free, to understand the real effort.
- Client side: (number of key users × days committed per week × duration) + project manager’s time + sponsor and finance time + data preparation (IT).
- Ancillary costs: test environment, possible outside support for anonymization or POC management.
The client-side cost is often the heaviest and the least visible: it is the one to present to the executive committee to get the commitment accepted. Compare this total with the value of the target contract and the cost of a wrong choice: that comparison is what justifies the POC, or not.
POC Checklist
Here is the checklist to run through before launching your POC.
Scoping
- Hypothesis to validate stated in one sentence
- Two to three vendors at most selected
- Sponsor named, go/no-go decision dated
- Three to five end-to-end scenarios, including at least one exception scenario
- One-page sheet per scenario, validated by the key user concerned
Data
- Extract taken from your own systems, anonymization validated by the DPO
- Minimum volume defined and recorded in the scoping document
- Traceability of data rework required
- Deletion of data at the end of the POC provided for in the contract
Criteria
- Go/no-go scorecard signed before kickoff
- Weighted criteria, written decision rule
- Thresholds not revisable without the sponsor’s agreement
Contract
- Cost allocation specified
- Duration, milestones and firm end date
- Ownership of deliverables secured
- Exit clause with no compensation, prices held for a defined period
- Named team members
Management
- Key users available, workload validated by their managers
- Weekly meeting and mid-point workshop scheduled
- Gap log kept up to date
- Key users at the controls from the second half
Readout
- Scorecard filled in scenario by scenario
- Gaps converted into requirements-document items
- Actual times carried into the schedule
- POC commitments carried into the contract
Going Further
The POC validates the product; you still have to choose who will implement it. Download our 100-point scoring grid to compare your integrators objectively, alongside the checklist above. If you are preparing a POC in your company and would like an outside view on the scope, the go/no-go scorecard or the contract framework, you can contact DigitsLane to discuss it.